Page 2 of 2 FirstFirst 1 2
Results 21 to 35 of 35

Thread: Real World Beam Failure Analysis

  1. #21
    Lead Engineer Cake of Doom's Avatar
    Join Date
    Aug 2012
    Location
    UK
    Posts
    433
    The motor is suspended from the beam using a cable. Think of how a "normal" hoist works, then turn it upside down.

    2b0396a3-888f-4c04-b1d3-faf14dd78ed1.jpg

  2. #22
    Principle Engineer
    Join Date
    Mar 2011
    Posts
    175
    "Ok, fair enough.
    But I'm showing that it would take well over 200,000 pounds of force to bend a schedule 40 pipe 3/4 of an inch over a span of 10 inches."

    You were assuming elastic deformation which it was NOT. It failed at a much smaller load and subsequently deformed 3/4 inch

    To do this problem you need an accurate assessment of the dynamic load ( dragging the load up a chain under the worst conditions, namely startup when the motor accelerates the load.

    You need the maximum motor startup torque which may be as much as 3 to 5X the nominal motor design torque.
    Next you write the equation
    T*2*Pi=F*x
    which is the energy equation
    x= the distance the load climbs for one revolution of the motor shaft
    T= maximum torque delivered by motor
    F= the maximum force applied to the chain that lifts the load and is the pipe design force.
    On top of this you need a factor of safety of at least 3.
    Not so simple. DO NOT use the weight of the load for the design calculation.

  3. #23
    Engineer PierArg's Avatar
    Join Date
    Mar 2013
    Location
    Italy, Bologna
    Posts
    27
    I thought the motor was on the top, as I drew.

    What I have drawn is just a simple scheme.
    Attached Files Attached Files

  4. #24
    Lead Engineer Cake of Doom's Avatar
    Join Date
    Aug 2012
    Location
    UK
    Posts
    433
    Quote Originally Posted by PierArg View Post
    I thought the motor was on the top, as I drew.

    What I have drawn is just a simple scheme.
    Now I see where you were getting the Torque from! Put the motor over the load and you got it. The motor then winds the cable in to it's self (like a man climbing a rope) to lift both the load and the motor.

  5. #25
    Engineer PierArg's Avatar
    Join Date
    Mar 2013
    Location
    Italy, Bologna
    Posts
    27
    Thanks! Now i've understood.
    I supposed the motor was on the top because there is only one cable.
    Last edited by PierArg; 03-08-2013 at 09:57 AM.

  6. #26
    Project Engineer
    Join Date
    Feb 2011
    Location
    Spokane, WA
    Posts
    130
    pipe failure .jpg

    Point of clarification:

    There is no torsion load on the pipe.
    As pictured above, the motor hangs from a wire rope.
    The wire rope is pulled up (by a rigger) between two C channel beams,
    and the pipe is inserted into a loop of the wire rope, as shown.

    The motor then climbs its own chain, lifting the load attached underneath (not shown).
    Last edited by dalecyr; 03-09-2013 at 01:57 PM.

  7. #27
    Project Engineer
    Join Date
    Feb 2011
    Location
    Spokane, WA
    Posts
    130
    Zeke:

    Thanks for your guidance on this problem.

    And thanks for that formula, I haven't used that one before.
    We rarely have the information available to use it though.

    However, what we do have is a industry standard rule of thumb
    to calculate the dynamic load when using a specific brand / model hoist.
    (The standard hoist in this industry)

    That rule of thumb has been verified in a lab and in the field (many times)
    by direct measurements using a load cell.

    It is "Dynamic Load = Load x 1.5"

    (it is actually a range of 1.25 to 1.5,
    but we always use the higher value of 1.5)

    So the dynamic load is a relatively known quantity.

    Using a maximum weight of 1200 pounds as claimed by the show,
    the potential dynamic load is 1800 pounds.

    Using a FOS of 5 (industry standard for the pipe as used in this application),
    the pipe design force is 9000 pounds.

    Since I am (now) not assuming elastic deformation,
    where do I go from here?

  8. #28
    Project Engineer
    Join Date
    Feb 2011
    Location
    Spokane, WA
    Posts
    130
    In thinking about this some more,
    I don't see how the motor start/stop dynamic load can possibly deform that pipe in that configuration.

    That type of deformation would have to come from a shock load.
    For example, while the point was being let down to the deck,
    maybe it caught on something, the chain went slack,
    then the load slipped and fell, creating a shock load on the pipe / rigging.

    A shock load can get pretty high very quickly.
    And shock loads are not common, but they are not rare in this industry either.

    A shock load is easy to calculate;
    the equation is well known and relatively simple,
    and the parameters are usually readily available.

    But what I am more interested in
    is how to calculate the stress needed to deform that pipe in this configuration.
    The "beam" is so short that I'm not sure the 'beam bending' equation is the correct one to use.
    The specific situation is almost more of a 'crush resistance' calculation.

    If the beam bending equation is the correct one to use,
    I'm getting a number so high that other elements would fail long before the pipe would.

    And Zeke hinted that the beam bending equation is not the right way to go about it anyway.
    I'll do the work, make the calculations, look up the numbers.
    I don't want anybody to solve the math or just provide the solution.
    But I sure could use a hand being pointed in the right direction...

  9. #29
    Associate Engineer
    Join Date
    Mar 2013
    Posts
    4
    The load required to reach yield (assuming 30 ksi), is about 4000 lbs. That is when your pipe will permanently deform.

  10. #30
    Project Engineer
    Join Date
    Feb 2011
    Location
    Spokane, WA
    Posts
    130
    I'd sure like to see the math / table / whatever on that.

  11. #31
    Associate Engineer
    Join Date
    Mar 2013
    Posts
    4
    See image below

    8hjchY3.jpg
    Last edited by Kelly_Bramble; 03-10-2013 at 09:29 AM.

  12. #32
    Project Engineer
    Join Date
    Feb 2011
    Location
    Spokane, WA
    Posts
    130
    Thank you.

  13. #33
    Project Engineer
    Join Date
    Feb 2011
    Location
    Spokane, WA
    Posts
    130
    Kelly:
    Any chance of adding this equation to the site?

  14. #34
    Quote Originally Posted by dalecyr View Post
    Kelly:
    Any chance of adding this equation to the site?
    I think we do...

    http://www.engineersedge.com/beam_be..._bending15.htm

    Needs an associated calculator...
    Last edited by Kelly_Bramble; 03-11-2013 at 10:21 PM.

  15. #35
    Principle Engineer
    Join Date
    Mar 2011
    Posts
    175
    "Ok, fair enough.
    But I'm showing that it would take well over 200,000 pounds of force to bend a schedule 40 pipe 3/4 of an inch over a span of 10 inches.

    (I=.3)

    Does that sound right?"


    No, what you did was use elastic theory to get the deflection.
    That deflecrttion was the resuly of a yield load and most of it was plastic deformation after yield.

    Your problem is simple, it was simply underdeigned

    To do it right,



    1 find the maximum starting torque the motor can put from which you get the corresponding tension in the wire rope.

    Apply a factor of safety of at least 2.5

    Use beam theory to keep teh flexural stress less than the yield stress using the design force.

Page 2 of 2 FirstFirst 1 2

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •